Karachi building chief removed after collapse kills four and leaves 17 missing

Karachi building chief removed after collapse kills four and leaves 17 missing

By Staff Reporter

KARACHI: The official in charge of regulating construction in Karachi was removed on Thursday, a day after a six-storey building approved for only two floors collapsed in the city, killing at least four people with 17 more reported missing.

Waseem Shamshad, who served as both Sindh’s local government secretary and director general of the Sindh Building Control Authority (SBCA), lost both posts on the orders of Chief Minister Murad Ali Shah.

Shah, chairing a high-level meeting, also ordered the removal of East Deputy Commissioner Nasrullah Abbasi and East Senior Superintendent of Police Zubair Sheikh over “negligence”, his office said. Shah directed that Shamshad’s services be surrendered to the federal government, which he asked to suspend the officer and order a formal inquiry. The Services, General Administration and Coordination Department notified the transfer of the BS-21 officer “with immediate effect”. Bilal Memon, chairperson of the Inspection, Enquiries and Implementation Team Department, was named local government secretary. Abid Saleem was appointed to head the SBCA in Shamshad’s place.

The chief minister further ordered the suspension of 16 SBCA officials and an inquiry into their conduct. He told police to arrest the owner, Salman Tahir, and the builder, Zeeshan, “immediately”, and instructed that the architect and structural engineer be brought into the investigation to establish whether the work complied with approved plans, building regulations and safety standards. Any other SBCA employee found responsible, he said, would face strict action after a “comprehensive and transparent” probe.

His office said he would not tolerate negligence that costs lives or causes suffering, and that public safety must remain the “foremost responsibility” of every government department.

At a press conference later, Shah said the 16 or 17 SBCA officers had been suspended for misconduct and that he wanted a legal case filed against them so they could be terminated under law and an example set. “We are going to have a reset in the Sindh Building Control Authority.”

He also disclosed the scale of the problem facing the authority. “At least 123 buildings in this city were being constructed under stay orders,” he said, adding that work on them had now been halted. The collapsed building, he said, was among them. He had asked the provincial law minister to approach the chief justice, and the court had been requested to decide all 123 cases within 15 days.

The meeting was attended by Local Government Minister Syed Nasir Hussain Shah, Home Minister Ziaul Hasan Lanjar, Karachi Mayor Murtaza Wahab, Chief Secretary Asif Hyder Shah and Karachi Commissioner Hassan Naqvi.

The building, a ground-plus-five-storey structure with a penthouse on 600 square yards in Baloch Colony, came down around 1pm on Wednesday, with more than 20 workers reported to be on site. Officials and witnesses said it fell while work to dig a borehole was under way.

The East deputy commissioner told reporters on Wednesday that the SBCA had approved a ground-plus-one building. The owner, he said, had built six storeys. When the SBCA tried to halt construction, the owner went to court and obtained an order against the authority, and the SBCA took no further action. Shah put the approved height at two floors, including the ground floor, and said such large-scale violations could not have happened without the involvement or negligence of government officials. He called the collapse not merely an accident but criminal negligence.

Rescue 1122 said teams had entered the collapsed structure and were searching inside, and that a wall of an adjoining vacant plot had been razed to open access. Its spokesperson, Hassaan Ul Haseeb Khan said an information desk had been set up with the East district administration and that families of 17 missing people had come forward. There was no official confirmation of that figure. On Wednesday Shah had said around 10 people were reported missing, and that the number inside was unclear because several contractors worked at the site.

At the information desk, relatives showed officials photographs of the missing on their phones, AFP reported. Three bodies and 14 injured were taken to the Jinnah Postgraduate Medical Centre (JPMC). Thirteen of the injured have since been discharged and one remains in hospital.

A first information report was registered at Tipu Sultan police station on Wednesday on the complaint of a Sindh Local Government Department official. It invokes Pakistan Penal Code sections covering intentional murder, a public servant concealing a design to commit an offence, mischief causing damage, hurt caused by a rash or negligent act, abetment and acts done in furtherance of common intention.

The building’s four owners, including Tahir, along with the builder, architect, structural engineer and contractors are nominated. Ten people in all are named in the case. The complainant alleged poor-quality material was used and that the suspects, in collusion with officials of several government departments, built additional structures in breach of the approved plan.

Police have arrested four suspects, including owner Saad Tahir and three contractors. They were produced before the judicial magistrate (south) on Thursday, who granted police five days’ physical remand.

The commissioner’s office said 12 other under-construction buildings in the same housing society had been sealed. The collapse follows a gas explosion earlier this year that brought down part of a residential building in Soldier Bazaar, killing at least 15 people, and the Lyari collapse in July 2025, in which 27 died in a building already declared uninhabitable.

Copyright © 2021 Independent Pakistan | All rights reserved